Subject:
|
2.3 Change Order for ASC Parking Lot
|
Strategic Plans:
|
2020-2025 OPERATIONS In TUSD 202, we will strive to elevate the educational environment through improved facilities, services, and infrastructure resulting in tangible and measurable outcomes.
|
Attachments
|
|
File Attachment:
|
|
Summary:
|
Change Order for ASC parking lot to replace the South set of stairs during the project, and add a flume along the side walk as well as a curb along the limestone retaining wall in the alley.
|
Funding:
|
Funding for this additional work will be allocated from the 2023-24 Capital Improvement Budget with funds that were available based on other projects coming in under budget.
|
Recommendation:
|
Motion to accept and approve the change order provided by Barkley Asphalt for the additional work during the parking lot replacement at the ASC.
|